Tab 1: Q1 Project Status (March 31)
Project ID | Manager | Budget (USD) | Status | Expected Completion |
P-101 | A. Smith | $150,000 | 75% Complete | May 15 |
P-102 | B. Jones | $220,000 | 50% Complete | June 30 |
P-103 | A. Smith | $90,000 | 95% Complete | April 10 |
P-104 | C. Davis | $300,000 | 25% Complete | July 20 |
Tab 2: Departmental Notes
- A. Smith: Has requested a $20,000 budget increase for P-101 to cover unexpected hardware costs. If approved, P-101’s expected completion date is unlikely to change.
- B. Jones: Project P-102 is currently behind schedule due to resource allocation conflicts. It requires an additional two weeks of development time to maintain the current budget.
- C. Davis: P-104’s budget is firm, but its scope is being reviewed. The earliest possible completion date for any project is April 1.
Based on the information in both tabs, which of the following statements is definitely true?
Correct!
Wrong!
If the budget increase for P-101 is approved, what will be the total combined budget for all projects managed by A. Smith?
Correct!
Wrong!
Which manager has the highest total initial budget responsibility?
Correct!
Wrong!