Tab 1: Q1 Project Status (March 31)

Project ID Manager Budget (USD) Status Expected Completion
P-101 A. Smith $150,000 75% Complete May 15
P-102 B. Jones $220,000 50% Complete June 30
P-103 A. Smith $90,000 95% Complete April 10
P-104 C. Davis $300,000 25% Complete July 20

Tab 2: Departmental Notes

  • A. Smith: Has requested a $20,000 budget increase for P-101 to cover unexpected hardware costs. If approved, P-101’s expected completion date is unlikely to change.
  • B. Jones: Project P-102 is currently behind schedule due to resource allocation conflicts. It requires an additional two weeks of development time to maintain the current budget.
  • C. Davis: P-104’s budget is firm, but its scope is being reviewed. The earliest possible completion date for any project is April 1.
0%

Based on the information in both tabs, which of the following statements is definitely true?

Correct! Wrong!

If the budget increase for P-101 is approved, what will be the total combined budget for all projects managed by A. Smith?

Correct! Wrong!

Which manager has the highest total initial budget responsibility?

Correct! Wrong!